We are glad to report the following key progress.

The following are the key mile stones for the project.

  • Start date of Civil Construction           :   15 March 2015
  • Completion of Work at site                :   28 September 2016
  • Kiln Firing date                                 :   1st October 2016
  • First Bag of Cement                          :   15 October 2016
  • Commission Completion and handover :    31st December 2016

As at January 31st,

  • 90 % of the equipment is at site
  • 90 % of the Civil Construction is completed
  • 20 % of the Erection work is completed
  • 75 % of the total Project is completed
 